Work Between Saturday, February 22 and Saturday, March 7, 2020


Mayor Bowser is committed to eliminating all roadways, alleys, and sidewalks in poor condition in Washington, DC by 2024 through the PaveDC initiative. This publication lists all of the road, alley, and sidewalk paving projects that will be under construction during the next two weeks. The 2019 Paving Plan is now live on the PaveDC website and includes a new tab for sidewalks scheduled for repair, in the coming weeks DDOT will also post the markings plan for the 2019 season.For more information about these projects, please visit DDOT's interactive tool, PaveDC.

Please note: Work may be adjusted depending on weather and other conditions. Additional projects may be added to this list. DDOT contacts residents and businesses within the work zones before work begins. Unless otherwise noted, work is not conducted on weekends.


Citywide Pavement Restoration Projects

As part of DDOT's commitment to improving and restoring local roadways, activities will be conducted at the following locations throughout the following two weeks, weather permitting:

Ward 5

  • South Dakota Avenue NE, V Street NE and Bladensburg Road NE (Crack Sealing)

Ward 8

  • Martin Luther King Jr. Avenue SE, between Good Hope Road SE and Howard Road SE (Crack Sealing)

Citywide Sidewalk Restoration Projects

As part of DDOT's commitment to the improvement and restoration of local sidewalks, construction activities will occur at the following locations throughout the next two weeks.

Ward 2

  • 15th Street NW, between Constitution Avenue NW and I Street NW
  • Vermont Avenue NW, between Logan Circle NW and R Street NW
  • 35th Street NW, between Winfield Lane NW and Q Street NW

Ward 4

  • Piney Branch Road NW, between Georgia Avenue NW and 13th Street NW
  • New Hampshire Avenue NE, between Oneida Street NE and Eastern Avenue NE

Ward 5

  • Morse Street NE, between Trinidad Street NE and Holbrook Street NE
  • R Street NW, between 4th Street NW and 5th Street NW
  • 21st Place NE, between Maryland Avenue NE and M Street NE

Ward 6

  • 7th Street SE, between South Carolina Avenue SE and G Street SE

Ward 8

  • Ridge Place SE, between 13th Street SE and 14th Street SE

Citywide Alley Restoration Projects

DDOT is improving alleys across the city. Once work begins, access to parts of the alley under construction will be closed, and parking is restricted. In emergency situations, access may be permitted by notifying DDOT. Work is estimated to take about two weeks, weather permitting. DDOT will be working in the following alleys this week:

Ward 1

  • Square 2829, bound by 11th Street NW, 13th Street NW, Otis Street NW and Spring Place NW
  • Square 2538, bound by Kalorama Road NW, Columbia Road NW, 19th Street NW and 20th Street NW

Ward 2

  • Square 0177, bound by T Street NW, 16th Street NW, Swann Street NW and New Hampshire Avenue NW
  • Square 2513, bound by Florida Avenue NW, 22nd Street NW, R Street NW and Massachusetts Avenue NW

Ward 4

  • Square 2790, bound by Fort Stevens Drive NW, 13th Street NW, Rittenhouse Street NW and 14th Street NW

Ward 5

  • Square 0519, bound by Florida Avenue NW, 3rd Street NW, 4th Street NW and R Street NW
  • Square 3555, bound by Channing Street NE, 3rd Street NE, Bryant Street NE and 4th Street NE

If you live near any of the project areas, please remove your vehicles by the posted times, and encourage your neighbors to do the same.