Weekly Construction Report: Work Between Saturday, September 28 and Saturday, October 12, 2019

Friday, September 27, 2019

Weekly Construction Update Banner

Work Between Saturday, September 28 and Saturday, October 12, 2019


Mayor Bowser is committed to eliminating all roadways, alleys, and sidewalks in poor condition in Washington, DC by 2024 through the PaveDC initiative. This publication lists all of the road, alley, and sidewalk paving projects that will be under construction during the next two weeks. The 2019 Paving Plan is now live on the PaveDC website and includes a new tab for sidewalks scheduled for repair, in the coming weeks DDOT will also post the markings plan for the 2019 season. For more information about these projects, please visit DDOT's interactive tool, PaveDC.

Please note: Work may be adjusted depending on weather and other conditions. Additional projects may be added to this list. DDOT contacts residents and businesses within the work zones before work begins. Unless otherwise noted, work is not conducted on weekends.


Citywide Pavement Restoration Projects

As part of DDOT's commitment to improving and restoring local roadways, activities will be conducted at the following locations throughout the following two weeks, weather permitting:

Ward 3

  • Sherier Place NW, between Cathedral Avenue NW and Chain Bridge Road NW
  • Overlook Road NW, between Rockwood Road Parkway NW and Glenbrook Road NW
  • Glenbrook Road NW, between Millwood Lane NW and Overlook Road NW
  • Macomb Street NW, between Potomac Avenue NW and MacArthur Boulevard NW
  • Newark Street NW, between Sherier Place NW and MacArthur Boulevard NW
  • Potomac Avenue NW, between Newark Street NW and Macomb Street NW
  • Burlington Place NW, between 46th Street NW and 44th Street NW
  • Ingomar Street NW, between Connecticut Avenue NW and 38th Street NW
  • Patterson Street NW, between Broad Branch Road NW and Chevy Chase Parkway NW
  • Jenifer Street NW, between Connecticut Avenue NW and 39th Street NW
  • Jocelyn Street NW, between Reno Road NW and 39th Street NW
  • Fulton Street NW, between Bellevue Terrace NW and 38th Street NW

Ward 4

  • Georgia Avenue NW, between Ingraham Street NW and Quincy Street NW
  • Alaska Avenue NW, between 16th Street NW and Holly Street NW
  • 14th Street NW, between Arkansas Avenue NW and Perry Street NW

Ward 6

  • O Street NW, between 8th Street NW and 9th Street NW
  • Gales Street NE, between 18th Street NE and 19th Street NE

Ward 8

  • Bruce Place SE, between Ainger Place SE and Raynolds Place SE
  • Ainger Place SE, between Bruce Place SE and Alabama Avenue SE
  • Langston Place SE, between Ainger Place SE and Raynolds Place SE
  • 18th Street SE, between Alabama Avenue SE and Trenton Place SE
  • Savannah Street SE, between 18th Street SE and Ridgecrest Court SE
  • 19th Street SE, between Trenton Place SE and Mississippi Avenue SE
  • Trenton Place SE, between 18th Street SE and 19th Street SE
  • Congress Street SE, between 13th Street SE and Savannah Street SE
  • Savannah Street SE, between 13th Street SE and Congress Street SE

Citywide Sidewalk Restoration Projects

As part of DDOT's commitment to the improvement and restoration of local sidewalks, construction activities will occur at the following locations throughout the next two weeks.

Ward 3

  • Foxhall Road NW, between Reservoir Road NW and Edmunds Street NW
  • Cathedral Avenue NW, between New Mexico Avenue NW and 44th Street NW
  • Brandywine Street NW, between 42nd Street NW and 45th Street NW

Ward 5

  • 12th Street NE, between Taylor Street NE and Upshur Street NE
  • 4th Street NW, between Q Street NW and R Street NW

Ward 6

  • E Street SE, between 15th Street SE and 17th Street NE

Ward 8

  • V Street SE, between 13th Street SE and 14th Street SE
  • 25th Street SE, between Minnesota Avenue SE and Park Place SE
  • U Street SE, between Fendall Street SE and 16th Street SE

Citywide Alley Restoration Projects

DDOT is improving alleys across the city. Once work begins, access to parts of the alley under construction will be closed, and parking is restricted. In emergency situations, access may be permitted by notifying DDOT. Work is estimated to take about two weeks, weather permitting. DDOT will be working in the following alleys this week:

Ward 1

  • Square 3046, bound by Lamont Street NW, Warder Street NW, Kenyon Street NW and 6th Street NW
  • Square 3032, bound by Otis Place NW, Princeton Place NW, Georgia Avenue NW and Warder Street NW

Ward 2

  • Square 0250, bound by 13th Street NW, I Street NW, H Street NW, New York Avenue NW and 14th Street NW

Ward 3

  • Square 1496, bound by Brandywine Street NW, Butterworth Place NW, 49th Street NW and 48th Street NW

Ward 7

  • Square 5279, bound by Southern Avenue SE, 58th Street SE, and East Capitol Street NE

Ward 8

  • Square 6124, bound by 8th Street SE, Yuma Street SE and Condon Terrace SE

If you live near any of the project areas, please remove your vehicles by the posted times, and encourage your neighbors to do the same.