Temporary Lane Closures in the I-295 Corridor for the Week of Sept 9

Friday, September 7, 2018



FOR IMMEDIATE RELEASE
Media Contacts

Temporary Lane Closures in the
I-295 Corridor for the Week of Sept 9

(Washington, DC)—The District Department of Transportation (DDOT) will temporarily close single lanes, ramps and shoulders on the following roadways to perform construction activities along the I-295 /DC 295 corridor. 

The following single lane, ramp, and shoulder closures will be in place daily from 9:30 am to 3:30 pm, Monday, September 10, 2018, through Saturday, September 15, 2018, weather permitting:

  • I-295 northbound between South Capitol Street (south of Exit 2) to Suitland Parkway (Exit 3A)
  • I-295 southbound between South Capitol Street (south of Exit 2) to Laboratory Road (Exit 1)
  • Potomac Avenue SE/SW between First Street, SE and Second Street, SW
  • South Capitol Street, SE/SW between Firth Sterling Avenue, SE and N Street, SE
  • Suitland Parkway, SE between Martin Luther King, Jr. Avenue, SE and South Capitol Street
  • Firth Sterling Avenue, SE between South Capitol Street and Howard Road, SE
  • Howard Road, SE between Firth Sterling Avenue, SE and Suitland Parkway, SE

The following single lane, ramp, and shoulder closures will be in place nightly from 9:00 pm to 5:00 am, Sunday, September 9, 2018, through Friday, September 14, 2018, weather permitting:

  • I-295 northbound between South Capitol Street (south of Exit 2) to Suitland Parkway (Exit 3A)
  • I-295 southbound between Suitland Parkway (Exit 4A) to Laboratory Road (Exit 1)
  • DC 295 northbound between 11th Street (Exit 5C) and Pennsylvania Avenue (Exit 1A)
  • South Capitol Street, SE/SW between Firth Sterling Avenue, SE and N Street, SE
  • Suitland Parkway, SE between Martin Luther King, Jr. Avenue, SE and South Capitol Street, SE
  • Firth Sterling Avenue, SE between South Capitol Street, SE and Howard Road, SE
  • Howard Road, SE between Firth Sterling Avenue, SE and Suitland Parkway, SE
  • I-295 northbound off-ramp to westbound Suitland Parkway, SE (Exit 3B). Signed detour will be in place for closure.
  • I-295 southbound off-ramp to eastbound Suitland Parkway, SE (Exit 4A). Signed detour will be in place for closure.
  • In addition, the access from Suitland Parkway westbound to Howard Road, SE will be closed starting on or about September 10, 2018. A signed detour route will be in place for this closure.

These closures are required for construction activities associated with multiple DDOT projects aimed at improving the I-295 / DC 295 corridor.